Avoiding Construction Disputes from Project Initiation: Key Decisions for Success

construction team reviewing documents with friendly handshake

(A Review of CRUX Report 2022)

As a construction dispute expert, one lesson I have learned over the years is that avoiding disputes begins long before shovels hit the ground. In fact, around 80% of construction dispute causes are directly tied to decisions made during project initiation. While this might sound discouraging, it is actually empowering. With the right strategies and early planning, disputes can be significantly reduced, saving time, money, and reputations.

Based on insights from the CRUX report, which examined over 1,600 global projects, the message is clear: most disputes can be traced back to decisions made at the start of the project. These early-stage decisions have a profound impact on the project’s ability to stay on track. Let’s dive into how making the right decisions from the outset can help you avoid costly disputes.

1. Project Scope Definition: The Foundation of Success

Defining the project scope clearly and thoroughly at the very beginning is arguably one of the most crucial steps. It’s not just about determining the “what” of the project but also understanding the “why” and “how.” Projects with ill-defined scopes are far more likely to face changes mid-construction, leading to delays, cost overruns, and disputes.

The CRUX report reveals that scope changes are one of the top causes of disputes worldwide. This isn’t surprising, as scope changes often trigger a domino effect, where budgets, schedules, and expectations all need to be adjusted. These adjustments lead to conflicts between contractors and project owners, as both sides often interpret the changes differently, with financial and legal consequences.

As a project manager, it's essential to invest time and resources into scope definition during the initiation phase. Engage all key stakeholders, including designers, contractors, and owners, to ensure everyone has the same understanding of the project’s objectives, deliverables, and limitations.

2. Design Development: Resolving Conflicts Before They Begin

Another significant contributor to construction disputes is poor design coordination. The CRUX findings highlight that design conflicts are prevalent across many regions, often stemming from insufficient coordination between teams or incomplete design documentation. This problem is particularly acute on large, complex projects where multiple subcontractors and designers are involved.

The solution here is simple yet often overlooked: involve all relevant parties early in the design process. This means working collaboratively with architects, engineers, contractors, and even end-users. Additionally, implementing a robust review process for design documents before construction begins is crucial to catch inconsistencies, omissions, or errors that could lead to disputes down the road.

Building Information Modeling (BIM) is a valuable tool in this respect. BIM enables more effective design coordination, allowing different teams to collaborate in a shared digital space. By detecting clashes and inconsistencies early, BIM can help resolve potential issues before they escalate into costly disputes.

3. Contractual Clarity: The Power of Detailed Agreements

One of the most recurring triggers of disputes, as per the CRUX report, is contract interpretation issues. These arise when contracts are unclear, incomplete, or interpreted differently by the parties involved. Disputes often occur when the terms of the contract—particularly around responsibilities, liabilities, and risk allocation—are ambiguous.

The best way to avoid this is through detailed and transparent contracts. Here’s where experienced contract administration comes into play. Legal and technical teams must ensure that contracts are not only well-drafted but also comprehensive enough to cover potential contingencies. Clauses related to force majeure, scope changes, time extensions, and cost overruns should be clearly defined to avoid differing interpretations.

Moreover, collaborative contract models are gaining traction in many parts of the world. These contracts focus on shared risk and reward, promoting teamwork rather than adversarial relationships. Early contractor involvement (ECI) and integrated project delivery (IPD) models encourage transparency and communication between all parties, significantly reducing the likelihood of disputes.

4. Risk Management: Identifying and Mitigating Risks Early

Every construction project comes with its share of risks—be it financial, technical, or logistical. The key to avoiding disputes is not to eliminate these risks entirely (an impossible task) but to identify them early and manage them effectively. According to the CRUX report, unforeseen physical conditions are a frequent source of conflict, particularly in regions with challenging environments.

Conducting comprehensive risk assessments at the project’s initiation can prevent many disputes. This involves working with consultants to identify potential site conditions, supply chain challenges, and regulatory changes that could affect the project. Additionally, risk registers should be developed and maintained throughout the project’s lifecycle, with specific mitigation strategies in place for high-risk areas.

Having clear risk-sharing provisions in contracts is also essential. Ensuring that the party best able to manage a specific risk takes responsibility for it will not only reduce disputes but also lead to more effective project delivery.

5. Procurement Strategy: Setting the Stage for Success

The method of procurement chosen during project initiation can greatly influence the likelihood of disputes. Traditional lump-sum contracts, which place most of the risk on contractors, are becoming less popular due to their adversarial nature. Instead, many projects are turning to collaborative procurement strategies that foster a partnership mentality.

The CRUX report highlights the growing trend of Design and Build (D&B) and Engineering, Procurement, and Construction (EPC) models, where contractors take a more active role in both the design and execution phases. These models can reduce the chances of disputes by ensuring that the contractor has input into the design process and is therefore better equipped to manage the risks associated with construction.

Selecting the right contractors and suppliers also plays a significant role. It’s crucial to conduct due diligence during the tendering process to ensure that the chosen contractors have the necessary expertise, experience, and financial stability to deliver the project as agreed.

6. Communication and Collaboration: The Human Factor

No matter how well-planned a project may be, communication breakdowns can quickly lead to disputes. Clear, consistent, and open lines of communication between all parties—owners, contractors, designers, and subcontractors—are essential for avoiding misunderstandings and managing expectations.

The CRUX report suggests that the human factor is often overlooked in dispute prevention strategies. Regular progress meetings, transparent reporting systems, and collaborative decision-making can go a long way in fostering a positive project environment where potential disputes are addressed early, before they escalate.

Conclusion: Proactive Planning is the Key to Success

While it is impossible to eliminate all disputes in construction, the data from the CRUX report makes it clear that most disputes stem from issues that can be addressed during the project initiation phase. By focusing on well-defined scopes, thorough design coordination, clear contractual terms, robust risk management, and effective communication, project leaders can set the foundation for a successful and dispute-free construction process.

As a construction dispute expert, I’ve seen firsthand the significant time and cost savings that can be achieved by taking a proactive approach to dispute avoidance. By making the right decisions at the start, you can not only avoid disputes but also ensure that your project is delivered on time, within budget, and to the satisfaction of all stakeholders.

Pauline Wiles

After writing and publishing 6 of my own books, I became a full-time website designer for other authors. I create modern, professional websites to help you grow your audience and make more impact with your work. British born, I’m now happily settled in California.

Next
Next

Cognitive or Neuroscience: The Missing Link in Causation Analysis of Construction Disputes